Jack Warner Parkway / Martin Luther King Jr. Boulevard Connector

Lead:  City of Tuscaloosa
Consultant:  Burk-Kleinpeter, Inc.
Estimated Project Costs:  $73M
Project Status:  

  • Phase 1: Construction is substantially complete with only punchlist items remaining. August 2023
  • Phase 2: Construction began in May 2022.  Expected completion November 2023

Phase 2 will be closed staring September 14th, and is expected to remain closed until sometime in late October.

  • Phase 3: Railroad premit in process.

 